[1]卜志鹏.大跨度CFST 系杆拱桥静动载试验分析研究[J].西安建筑科技大学学报:自然科学版,2015,47(03):388-391.[doi:10.15986/j.1006-7930.2015.03.014]
 BU Zhipeng.Study on the static and dynamic load test for long-span CFST tied arch bridge[J].J.Xi’an Univ. of Arch. & Tech.:Natural Science Edition,2015,47(03):388-391.[doi:10.15986/j.1006-7930.2015.03.014]
点击复制

大跨度CFST 系杆拱桥静动载试验分析研究()
分享到:

西安建筑科技大学学报:自然科学版[ISSN:1006-7930/CN:61-1295/TU]

卷:
47
期数:
2015年03期
页码:
388-391
栏目:
出版日期:
2015-06-30

文章信息/Info

Title:
Study on the static and dynamic load test for long-span CFST tied arch bridge
文章编号:
1006-7930(2015)03-0388-04
作者:
卜志鹏
(中铁第一勘察设计院集团有限公司,陕西 西安 710043)
Author(s):
BU Zhipeng
(China Railway First Survey and Design Institute Group Ltd.Xian 710043China)
关键词:
铁路桥CFST系杆拱桥静动载试验有限元分析校验系数
Keywords:
railway bridge CFST tied arch bridge static and dynamic test finite element analysis verification coefficient.
分类号:
U446
DOI:
10.15986/j.1006-7930.2015.03.014
文献标志码:
A
摘要:
包西铁路跨黄延高速公路大桥主桥为单跨128 m 的钢管混凝土(CFST)系杆拱桥.通过对该铁路大桥进行实桥静动载试验,研究了在静动载作用下大跨度CFST 系杆拱桥的结构特性、脱轨系数、加速度及振幅响应等关键参数,并与ANSYS 有限元分析结果进行了对比.发现大跨度CFST 系杆拱桥挠度和应力校验系数处于合理范围,结构各项关键参数满足规定要求.结果表明:该铁路大桥具有足够的强度和刚度,动力性能良好,满足设计的荷载等级和营运要求;有限元计算结果能够反映该桥梁结构静力及动力性能.本文研究结果对大跨度CFST 系杆拱桥的竣工验收及鉴定评价有重要指导意义.
Abstract:
Main bridge of Baoxi Railway across Huangyan Highway is a tied concrete-filled steel tubular (CFST) arch bridge with a single span of 128m. Static and dynamic test on this real bridge were conducted and key parameters such as structural characteristics, derailment coefficient, accelerations, amplitude response in action of static and dynamic loads were studied and compared with results of finite element method (FEM) analysis using ANSYS. All key parameter are identified to be good and the railway bridge has enough stiffness and strength, deflection and the stress calibration factor of the structure are at reasonable range, meeting requirements of codes and operating. FEM analysis results can show the static and dynamic characteristics. Results of the paper are important in guiding completion inspection and acceptance work, identification and evaluation work.

参考文献/References:

[1] 中华人民共和国铁道部.铁运函[2004]120 号. 铁路桥梁检定规范[S]. 北京: 中国铁道出版社, 2004.

The ministry of railways of the People’s Republic of China. Trains letter [2004] No. 120. Railway bridge verification code [S]. Beijing:China Railway Press, 2004.

[2] 高晓燕, 张浩, 张晓炜, 等. 蒲山特大桥静动载试验及质量评定[J]. 中外公路, 2010, 30(4): 360-364.

GAO Xiaoyan, ZHANG Hao, ZHANG Xiaowei, et al. PuShan bridge on static and dynamic load test and quality evaluation [J]. Journal of China and Foreign Highway, 2010 ,30(4):360-364.

[3] 孙建平. 大跨度铁路系杆拱桥静动载试验研究[J]. 铁道建筑, 2012(9): 29-32.

SUN Jianping. Long-span railway arc bridge static and dynamic load test research [J]. Railway Engineering, 2012(9): 29-32.

[4] 陈昀明, 韦建刚, 陈宝春. 泉州百崎湖大桥静动载试验分析研究[J]. 公路工程, 2009, 34(5): 104-108.

CHEN Yunming, WEI Jiangang, CHEN Baochun. Static and dynamic tests and analysis of baiji lake bridge [J]. Highway Engineering, 2009, 34(5): 104-108.

[5] 丘弋. 下承式系杆拱桥的荷载试验分析[J]. 中国勘察设计, 2012(8): 84-89.

QIU Yi. The load test analysis of a tied arch bridge [J]. China survey and design, 2012(8): 84-89.

[6] 中华人民共和国交通部.YC4-4/1982 大跨径混凝土桥梁的试验方法[S].北京: 人民交通出版社, 1982.

The ministry of communications of the People’s Republic of China.YC4-4/1982The test method of long-span concrete bridge [S]. Beijing: People’s Traffic Press, 1982.

[7] 中华人民共和国铁道部.铁建设函[2005]285 号. 新建时速200 公里客货共线铁路设计暂行规定[S]. 北京:中国铁道出版社, 2005.

The ministry of railways of the People’s Republic of China. Railwayconstruction letter [2005] No.285. New 200 km/h mixed collinear railway design regulations [S]. Beijing: China Railway Press, 2005.