[1]阮艳妹,徐文田,李牧羽.沿海复杂地层深基坑地下水控制引发的地表沉降规律分析[J].西安建筑科技大学学报(自然科学版),2023,55(05):712-719.[doi:10.15986/j.1006-7930.2023.05.010]
 RUAN Yanmei,XU Wentian,LI Muyu.Analysis of surface subsidence law caused by groundwater control of deep foundation pit in coastal complex strata[J].J. Xi’an Univ. of Arch. & Tech.(Natural Science Edition),2023,55(05):712-719.[doi:10.15986/j.1006-7930.2023.05.010]
点击复制

沿海复杂地层深基坑地下水控制引发的地表沉降规律分析()
分享到:

西安建筑科技大学学报(自然科学版)[ISSN:1006-7930/CN:61-1295/TU]

卷:
55
期数:
2023年05期
页码:
712-719
栏目:
出版日期:
2023-10-28

文章信息/Info

Title:
Analysis of surface subsidence law caused by groundwater control of deep foundation pit in coastal complex strata
文章编号:
1006-7930(2023)05-0712-08
作者:
阮艳妹徐文田李牧羽
(广州地铁设计研究院股份有限公司,广东 广州 510010)
Author(s):
RUAN Yanmei XU Wentian LI Muyu
(Guangzhou Metro Design & Research Institute Co.,Ltd., Guangzhou 510010, China)
关键词:
降水回灌试验地下水位地表沉降建筑物沉降回灌开启时间
Keywords:
precipitation recharge test water table surface subsidence building settlement recharge start time
分类号:
TU 463
DOI:
10.15986/j.1006-7930.2023.05.010
文献标志码:
A
摘要:
针对沿海深厚富水复杂地层开展了基坑降水回灌试验,分析了基坑降水回灌过程中地下水位、地表沉降和邻近建筑物沉降等基本规律.结果表明:深厚富水复杂地层降水会导致基坑周边地下水位迅速下降,同时将引起剧烈的地表沉降,当回灌量与抽水量逼近平衡时,地表沉降趋于稳定.基坑降水回灌过程中,地表沉降变化时程曲线会出现明显的转折点,回灌开始后地表沉降值仅有小幅度的抬升,但先期沉降基本无法恢复.回灌开启时间与地表最终沉降量呈现明显的相关性,但对地下稳定水位影响不显著,同抽同灌工艺对地表沉降控制的优势明显,好于先抽后灌及先灌后抽工艺.研究成果可以为类似工程的降水设计与环境控制提供数据支持.
Abstract:
The foundation pit dewatering and recharge test is carried out for the deep and complex waterrich strata in the coastal area, and the basic laws of groundwater level, surface subsidence and adjacent building subsidence during the foundation pit dewatering and recharge process are analyzed. The results show that the dewatering of deep waterrich complex strata will lead to the rapid decline of groundwater level around the foundation pit, and at the same time, it will cause severe surface subsidence. When the recharge and pumping amount approach the balance, the surface subsidence tends to be stable. In the process of dewatering and recharging of foundation pit, there will be an obvious turning point in the timehistory curve of surface settlement. After recharging, the surface settlement only rises slightly, but the early settlement can′t be recovered basically. The starting time of recharge is obviously related to the final settlement of the surface, but it has no significant effect on the stable groundwater level. The technology of simultaneous pumping and irrigation has obvious advantages in controlling the surface settlement, which is better than the first pumping and then irrigation or first irrigation and then pumping technology. The research results can provide data support for precipitation design and environmental control of similar projects.

参考文献/References:

[1]ZHANG Y Q, LI M G, WANG J H, et al. Field tests of pumping-recharge technology for deep confined aquifers and its application to a deep excavation [J]. Engineering Geology, 2017, 228: 249-259.

[2]周勇,王晓莉,朱彦鹏,等.兰州地铁湿陷性黄土深基坑在降低水位条件下的渗流稳定性分析 [J].中国铁道科学, 2017, 38(1): 86-94.
  ZHOU Yong, WANG Xiaoli, ZHU Yanpeng, et al. Seepage stability analysis of deep foundation pit of lanzhou metr under the condition of water level reduction in collapsible loesst[J]. CHINA RAILWAY SCIENCE, 2017, 38(1): 86-94.
[3]ZHENG G, ZENG C F, DIAO Y, et al. Test and numerical research on wall deflections induced by preexcavation dewatering [J]. Computers & Geotechnics, 2014, 62(oct.): 244-256.
[4]杨潇.多基坑深层承压水降水引起地表沉降规律研究[J].西安建筑科技大学学报(自然科学版), 2015, 47(1): 66-70.
  YANG Xiao. Study on the law of formations settlement induced by dewatering in deep confined aquifer in multiple excavations [J]. J. Xi′an Univ. of Arch. &Tech. (Natural Science Edition), 2015, 47(1): 66-70.
[5]SHEN S L. Numerical evaluation of land subsidence induced by groundwater pumping in Shanghai[J]. Canadian Geotechnical Journal, 2011, 48(9):1378-1392.
[6]张扬清,冉岸绿,武朝军,等.降压回灌作用下黏土的渗透特性试验研究[J].岩土工程学报, 2015(S1): 21-25.
  ZHANG Yangqing, RAN Anlü, WU Chaojun, et al. Experimental study on permeability properties of soft clay in process of pumping and recharge [J]. Chinese Journal of Geotechnical Engineering, 2015(S1): 21-25.
[7]郑刚,曹剑然,程雪松,等.天津第二粉土粉砂微承压含水层回灌试验研究[J].岩土工程学报, 2018, 40(4): 592-601.
  ZHENG Gang, CAO Jianran, CHENG Xuesong , et al. Experimental study on artificial recharge of second Tianjin silt and silty sand micro-confined aquifer [J]. Chinese Journal of Geotechnical Engineering, 2018, 40(4): 592-601.
[8]刘祥勇,宋享桦,谭勇,等.南通富水砂性地层地铁深基坑抽水回灌现场试验研究[J].岩土工程学报, 2020, 42(7): 1331-1340.
  LIU Xiangyong, SONG Xianghua, TAN Yong, et al. Field tests on groundwater recharge of deep excavations in Nantong water-rich sandy stratum [J]. Chinese Journal of Geotechnical Engineering, 2020, 42(7): 1331-1340.
[9]金小荣,俞建霖,祝哨晨,等.基坑降水引起周围土体沉降性状分析[J].岩土力学, 2005(10): 5460.
  JIN Xiaorong, YU Jianlin, ZHU Shaochen, et al. Analysis of behaviors of settlement of pit′s surrounding soils by dewatering [J]. Rock and Soil Mechanics, 2005(10): 54-60.
[10]李罡.基坑降水回灌技术在济南地铁中的应用 [J].施工技术, 2018, 47(1): 79-83.
  LI Gang. Application of foundation excavation dewatering and recharge technique in Jinan subway[J]. Construction Technology, 2018, 47(1): 79-83.
[11]瞿成松,徐丹.地下水回灌在地铁边基坑降水中的应用[J].岩土工程技术, 2012, 26(5): 4.
  QU Chengsong, XU Dan . Groundwater recharge of pit dewatering close to the metro[J]. Geotechnical Engineering Technique, 2012, 26(5): 4.
[12]WU Y X, LYU H M, SHEN J S, et al. Geological and hydrogeological environment in Tianjin with potential geohazards and groundwater control during excavation [J]. Environmental Earth Sciences, 2018, 77(10): 392.
[13]SHEN S L, TANG C P, BAI Y, et al. Analysis of settlement due to withdrawal of groundwater around an unexcavated foundation pit: Geo Shanghai International Conference 2006[C]//2015.
[14]LEUNG E, NG C. Wall and Ground movements associated with deep excavations supported by cast in situ wall in mixed ground conditions[J]. Journal of Geotechnical & Geoenvironmental Engineering, 2007,133(2):129-143.
[15]梅源, 袁一力, 胡长明, 等. 西安地铁深基坑变形模式统计规律分析[J]. 西安建筑科技大学学报(自然科学版), 2016, 48(3): 371-375.
  MEI Yuan, YUAN Yili, HU Changming, et al. Statistical analysis of the construction deformation model of the deep foundation pit in Xi′an Metro Station [J]. J. Xi′an Univ. of Arch. &Tech. (Natural Science Edition) , 2016, 48(3): 371-375.
[16]SHEN S L, WU Y X, XU Y S, et al. Evaluation of hydraulic parameters from pumping tests in multiaquifers with vertical leakage in Tianjin [J]. Computers and Geotechnics, 2015, 2015:196-207.
[17]王国富,王倩,路林海,等.济南轨道交通某深基坑降水与回灌数值分析[J].地下空间与工程学报, 2017, 13(5): 1280-1288.
  WANG Guofu, WANG Qian, LU Linhai, et al. Numerical analysis on dewatering and recharging of a deep foundation pit of inan railway[J]. Chinese Journal of Underground Space and Engineering, 2017, 13(5): 1280-1288.
[18]URBAN L V, CLABORN B J. Ogallala recharge with stormwater collected in playa lakes: Artificial recharge of ground water[C], 2015.
[19]TUGEL F, HOUBEN G J , GRAF T. How appropriate is the Thiem equation for describing groundwater flow to actual wells?[J]. Hydrogeology Journal, 2016, 24(8):2093-2101.
[20]伍毅敏, 吕康成, 郑颖人. 深基坑周边位移实时监测系统的研发[J]. 西安建筑科技大学学报(自然科学版), 2006(2): 194-198.
  WU Yimin, LU Kangcheng, ZHENG Yingren. Development of the monitoring system for instant displacement surrounding deep foundation pits[J]. J. Xi′an Univ. of Arch. &Tech. (Natural Science Edition) , 2006(2): 194-198.
[21]陆建生,潘伟强.上海某枢纽基坑工程浅层承压水回灌试验分析[J].地下空间与工程学报, 2014, 10(4): 9.
  LU Jiansheng, PAN Weiqiang. Test and analysis of artificial recharge to the shallow confined aquifer of deep foundation pit in Shanghai [J]. Chinese Journal of Underground Space and Engineering, 2014, 10(4): 9.
[22]许健,杨少飞,吴海洋,等.黄土地区深大基坑桩锚支护结构监测与数值分析[J].西安建筑科技大学学报(自然科学版), 2019, 51(4): 517-524.
  XU Jian, YANG Shaofei, WU Haiyang, et al. Monitoring and numerical analysis of pileanchor supporting structure for deep and large foundation pit in loess area [J]. J. Xi′an Univ. of Arch. &Tech. (Natural Science Edition) , 2019, 51(4): 517-524.
[23]党发宁,王海洋,高仓,等.超期服役粉细砂基坑变形时效性研究[J].西安建筑科技大学学报(自然科学版),2023,55(1):41-51.
  DANG Faning, WANG Haiyang, GAO Cang, et al. Study on deformation timeliness of excessive service siltfine sand foundation pit [J]. J. Xi′an Univ. of Arch. &Tech. (Natural Science Edition) , 2023, 55(1): 41-51.

备注/Memo

备注/Memo:
收稿日期:2022-07-26修回日期:2023-08-16
基金项目:住房和城乡建设部研究开发项目(2022-K-044)
第一作者:阮艳妹(1981—),女,本科,高级工程师,主要从事轨道交通结构设计及研究工作. E-mail: 3040383070@qq.com
更新日期/Last Update: 2023-11-03