[1]张 勇,张然然.地下综合管廊全寿命周期风险评估与分析[J].西安建筑科技大学学报(自然科学版),2019,51(02):294-300.[doi:10.15986/j.1006-7930.2019.02.021]
 ZHANG Yong ZHANG Ranran.Life-cycle risk assessment and analysis of underground comprehensive utility tunnel[J].J. Xi’an Univ. of Arch. & Tech.(Natural Science Edition),2019,51(02):294-300.[doi:10.15986/j.1006-7930.2019.02.021]
点击复制

地下综合管廊全寿命周期风险评估与分析()
分享到:

西安建筑科技大学学报(自然科学版)[ISSN:1006-7930/CN:61-1295/TU]

卷:
51
期数:
2019年02期
页码:
294-300
栏目:
出版日期:
2019-04-28

文章信息/Info

Title:
Life-cycle risk assessment and analysis of underground comprehensive utility tunnel
文章编号:
1006-7930(2019)02-0294-07
作者:
张 勇 张然然
(西安建筑科技大学 管理学院,陕西 西安 710055)
Author(s):
ZHANG Yong ZHANG Ranran
(Management School , Xi’an Univ. of Arch . & Tech .Xi’an 710055China)
关键词:
地下综合管廊风险评估风险分析模糊层次分析法(IFAHP)决策实验和评价实验室法(DEMATEL)
Keywords:
the underground comprehensive utility tunnel risk assessment risk analysis IFAHPDEMATEL
分类号:
TU714,X947
DOI:
10.15986/j.1006-7930.2019.02.021
文献标志码:
A
摘要:
参考相关文献和法规,结合地下综合管廊自身特点,建立全寿命周期风险评估指标体系;采用模糊层次分析法(IFAHP)进行风险评估,得到风险因素总排序,并利用决策实验和评价实验室法(DEMATEL),从风险因素内部影响关系入手,分析关键风险,找出原因因素和结果因素。结果表明,原因因素为:施工方缺乏管廊施工经验,不可抗力风险,缺乏相关政策、法规支持,材料进场检验及保管不到位,设备进场检验、施工操作及保养不到位,地下空间和土地的使用权获取难度大;结果因素为:安全施工风险;项目融资难度大,收费方式选择不合理或未进行及时调整,运营责任不明确。有利于针对性的风险控制,降低事故发生率,为地下综合管廊全寿命周期风险管理提供重要参考。
Abstract:
With reference to relevant literature and regulations , combined with the characteristics of the underground comprehensive utility tunnel, the life-cycle risk assessment index system is established. Use IFAHP for risk assessment, obtain a total ranking of risk factors . DEMATEL method is adopted to analyzed the key risk s, the cause factors and the result factors are found. The results show that the reasons are: the construction lacks the experience of underground comprehensive utility tunnel, force majeure risk, lack of relevant policies and regulations, insufficient material inspection and storage, equipment entry inspection, construction operation and maintenance are insufficient, and the access to underground space and land are difficult to obtain; The result factors are: safety co nstruction risk; project financing is difficult, the charging method is unreasonable or not adjusted in time, and the operational responsibility is not clear. It is conducive to targeted risk control, reducing the incidence of accidents, and providing an important reference for the life-cycle risk management of underground comprehensive utility tunnel

参考文献/References:

[ ] Canto.Perello J,Curiel-Esparza.Human factors engineering in utility Tunnel design[J]. Tunneling and Underground Space Technology,2001,16(3):211-215.[ ] 杨秋侠,仵宁,柴攀.城市综合管廊线性定位优化[J].土木工程学报,2017(5):123-128.YANG Qiu-xia, WU Ning, Chai Pan. Linear location op-timization of underground comprehensive utility tunnel[J]. China Civil Engineering Journal, 2017(5):123-128.[ ] 邵帅,胡晓欢,代婧瑜等.综合管廊穿越既有铁路段铁路加固方案[C]//第九届建筑物改造与病害处理学术研讨会.第九届建筑物改造与病害处理学术研讨会论文集. 2011:230-232.SHAO Shuai, HU Xiaohuan, DAI Jingyu et al. Rein-forcement of underground comprehensive utility tunnel through existing railway sections [C]//The 9th Symposium on Building Renovation and Disease Treatment . Proceedings of the 9th Symposium on Building Recon-struction and Disease Treatment. 2011: 230-232.[ ] 桂小琴,王望珍,章帅龙.地下综合管廊建设融资的激励机制设计[J].地下空间与工程学报,2011(4):633-636.GUI Xiao-qin, WANG Wang-zhen, ZHANG Shuai-long. Incentive mechanism design for underground comprehen-sive utility tunnel construction financing[J]. Chinese Journal of Underground Space and Engineering,2 011(4):633-636.[ ] 刘慧慧,孙剑,李飞飞.城市地下综合管廊应用PPP模式的VFM评价[J].土木工程与管理学报,2016(4):122-126.LIU Hui-hui,SUN Jian,LI Fei-fei. VFM evaluation of un-derground comprehensive utility tunnel application PPP model[J].Journal of Civil Engineering and Management, 2016(4):122-126.[ ] 李芊,赵雪婷.综合管廊全寿命周期风险分析[J].价值工程,2017(10):240-242.LI Qian, Zhao Xue-ting. Life Cycle Risk analysis ofunderground comprehensive utility tunnel[J]. Value En-gineering, 2017(10): 240-242.[ ] 韦海民,刘武岩.城市综合管廊施工过程中的风险识别过滤研究[J].建筑技术,2017(9):927-930WEI Hai-min, LIU Wu-yan. Study on risk identification and filtering in construction of underground comprehensive utility tunnel[J].Architecture Technology,2017(9):927-930.[ ] 王曦,祝付玲.基于博弈分析的城市综合管廊收费对策研究[J].地下空间与工程学报,2013,9(1):197-203.WANG Xi,ZHU Fu-ling. Research on countermeasures of underground comprehensive utility tunnel charge based on game analysis[J].Chinese Journal of Underground Space and Engineering,2013,9(1):197-203

相似文献/References:

[1]韦海民,苏桐.地下综合管廊PPP项目模式选择研究[J].西安建筑科技大学学报(自然科学版),2018,50(01):126.[doi:10.15986/j.1006-7930.2018.01.020]
 WEI HaiminSU Tong.Research on mode selection of utility tunnel PPP project[J].J. Xi’an Univ. of Arch. & Tech.(Natural Science Edition),2018,50(02):126.[doi:10.15986/j.1006-7930.2018.01.020]

备注/Memo

备注/Memo:
收稿日期:2018-09-12基金项目:陕西省重点研发计划—重点项目(2018ZDXM-SF-096)。第一作者:张勇(1965.9—),男,博士,教授级高工,主要从事项目管理、地下综合管廊等方面的研究。Email:xadayong@126.com.通讯作者:张然然(1993.8——),女,硕士,主要从事工程经济与管理等方面的研究。联系电话:15664671959,Email:1612350054@qq.com