[1]张润沂,郭炎乐,付建华,等.基于建筑信息模型的施工阶段进度-成本协同管理研究[J].西安建筑科技大学学报(自然科学版),2021,53(02):302-308.[doi:10.15986/j.1006-7930.2021.02.021]
 ZHANG Runyi,GUO Yanle,FU Jianhua,et al.Research on joint management of schedule and cost based on BIM in construction stage[J].J. Xi’an Univ. of Arch. & Tech.(Natural Science Edition),2021,53(02):302-308.[doi:10.15986/j.1006-7930.2021.02.021]
点击复制

基于建筑信息模型的施工阶段进度-成本协同管理研究()
分享到:

西安建筑科技大学学报(自然科学版)[ISSN:1006-7930/CN:61-1295/TU]

卷:
53
期数:
2021年02期
页码:
302-308
栏目:
出版日期:
2021-04-28

文章信息/Info

Title:
Research on joint management of schedule and cost based on BIM in construction stage
文章编号:
1006-7930(2021)02-0302-07
作者:
张润沂1郭炎乐2付建华2李红玲3
(1.武汉理工大学 土木工程与建筑学院,湖北 武汉 430070; 2.武汉市工程建设标准定额管理站,湖北 武汉 430020; 3.武汉宾孚建设工程顾问有限公司,湖北 武汉 430050)
Author(s):
ZHANG Runyi1 GUO Yanle2 FU Jianhua2 LI HongLing3
(1.School of Civil Engineering,Wuhan University of Technology,Wuhan 430070,China; 2.Wuhan Engineering Construction Standard Quota Management Station, Wuhan 430020,China; 3.Wuhan Binfo Construction Engineering Consulting Co., Ltd, Wuhan 430050,China)
关键词:
进度-成本协同管理 5D-BIM 施工阶段 改进挣值法 挣值曲线
Keywords:
joint management of schedule and cost 5D-BIM construction stage improved earned value method earned value curve
分类号:
TU714
DOI:
10.15986/j.1006-7930.2021.02.021
文献标志码:
A
摘要:
建设项目施工进度与成本目标值分配及控制是达成项目综合目标的关键工作之一,但由于相关计划活动数量众多且关联性强的特点,形成了工作精度要求高和工作难度大的矛盾和瓶颈问题.在深入分析该问题的基础上,利用BIM软件的搜索算法,准确快速地提取相关计划活动的工程量; 然后依据合同单价,计算相关活动成本; 并运用5D-BIM针对性地研发出改进的挣值绩效计算软件,结合进度管理模块和成本管理模块,形成进度-成本协同管理平台; 将成本-进度信息输入平台内,能准确生成挣值曲线,提供施工阶段进度-成本协同管理决策信息.实证分析结果表明,该方法能提高项目管控效率与联动性,提供更加有效的辅助决策支持.
Abstract:
The allocation and control of the construction’s schedule and cost target value in the construction project is one of the key tasks to achieve the overall project objectives. However, due to the large number of related planned activities and the strong correlation, the contradiction and bottleneck of high precision and difficult work has been formed a problem. Based on the in-depth analysis of the problem, using Revit’s search algorithm to get the quantities of the relevant planned activities accurately and quickly. Then calculating the relevant activity costs based on the contract unit price; Using 5D-BIM to develop improved earned value performance calculation software, combined with schedule management module and cost management module, forms a schedule-cost collaborative management platform; Inputting cost-schedule information into the platform,accurately calculate and generate earned value curve, and provide construction stage schedule-cost collaborative management decision information. The empirical analysis results show that this method can improve the efficiency and linkage of project management and control, and provide more effective auxiliary decision support.

参考文献/References:

[1]陈祥赟,董娜,熊峰,等. 基于BIM的某项目进度与成本控制研究[J].施工技术, 2014, 43(S2): 580-583.
CHEN Xiangyun, DONG Na,XIONG Feng, et al. Research on Schedule and Cost Control of a Project Based on BIM,[J].Construction Technology, 2014, 43(S2): 580-583.
[2]徐洪刚,胡鹏飞.工程项目成本、进度、质量集成控制的研究[J].科技管理研究,2006(3):132-133.
XU Honggang,HU Pengfei. Research on integrated control of cost, schedule and quality of engineering project[J].Science and Technology Management Research, 2006(3):132-133.
[3]TEICHOLZ, P M.Current needs for cost control systems. In Project controls: needs and solutions[J].ASCE,1987, 47-57.
[4]毕磊,于水,丁琼,等. 基于5D-BIM的高桩码头工程施工进度-成本实时控制[J].水运工程, 2017,(3): 189-193.
BI Lei, YU Shui, DING Qiong, et al.Duration and cost real-time control of high-piled wharf construction based on 5D-BIM.[J].Port&Waterway Engineering, 2017,(3): 189-193.
[5]黄建文,毛宇辰,王东,等.基于BIM的碾压混凝土坝施工进度-成本协同管理[J].水利水电科技进展, 2019, 39(5): 66-72, 88.
HUANG Jianwen, MAO Yuchen, WANG Dong, et al.Construction schedule-cost joint control of RCC dams based on BIM[J].Advances in Science and Technology of Water Resources, 2019, 39(5): 66-72, 88.
[6]WANG K C,WANG W C,WANG H H, et al. "Applying building information modeling to integrate schedule and cost for establishing construction progress curves." Automation in Construction 72(2016): 397-410.
[7]胡长明,熊焕军,龙辉元,等. 基于BIM的建筑施工项目进度-成本联合控制研究[J].西安建筑科技大学学报(自然科学版), 2014, 46(4): 474-478.
HU Changming,XIONG Huanjun,LONG Huiyuan, et al. Research on schedule-cost joint control of building construction project based on BIM.[J]J. Xi’an Univ. of Arch. & Tech.(Natural Science Edition),2014, 46(4): 474-478
[8]陈伟,武亚帅,邹松,等.基于SEM的装配式建筑建造成本影响因素分析[J].土木工程与管理学报,2019,36(5):50-55.
CHEN Wei,WU Yashuai,ZHOU Song, et al.Construction cost factor analysis of prefabricated building based on structural equation model[J].Journal of Civil Engineering and Management,2019,36(5):50-55
(编辑 桂智刚)