[1]宋战平,张 强,赵克明,等.基于现场监测及数值分析的隧道双导洞超前施工优化研究[J].西安建筑科技大学学报(自然科学版),2018,50(05):654-0661.[doi:10.15986/j.1006-7930.2018.05.006]
 SONG Zhanping,ZHANG Qiang,ZHAO Keming,et al.Optimization study of advanced double-drift tunnel construction based on on-site monitoring and numerical analysis[J].J. Xi’an Univ. of Arch. & Tech.(Natural Science Edition),2018,50(05):654-0661.[doi:10.15986/j.1006-7930.2018.05.006]
点击复制

基于现场监测及数值分析的隧道双导洞超前施工优化研究()
分享到:

西安建筑科技大学学报(自然科学版)[ISSN:1006-7930/CN:61-1295/TU]

卷:
50
期数:
2018年05期
页码:
654-0661
栏目:
出版日期:
2018-10-28

文章信息/Info

Title:
Optimization study of advanced double-drift tunnel construction based on on-site monitoring and numerical analysis
文章编号:
1006-7930(2018)05-0654-08
作者:
宋战平12张 强1赵克明1张学钢13张学文2王娟娟
(1. 西安建筑科技大学 土木工程学院,西安 710055;2. 中国铁建大桥工程局集团有限公司,天津 300300;3. 陕西铁路工程职业技术学院 渭南 714099)
Author(s):
SONG Zhanping12 ZHANG Qiang1 ZHAO Keming1 ZHANG Xuegang13 ZHANG Xuewen2 WANG Juanjuan1
(1. School of Civil Engineering, Xian University of Architecture and Technology, Xian 710055 , China; 2. China Railway Construction Bridge Engineering Bureau Group Co., Ltd., Tianjin 300300, China; 3. Shaanxi Railway Institute, Weinan 714099, China)
关键词:
隧道工程弱胶结粉细砂底部双导洞超前法现场监测数值模拟
Keywords:
tunnel engineering weak cemented fine sand bottom advanced double-drift method in-situ monitoring numerical simulation
分类号:
U 455.4
DOI:
10.15986/j.1006-7930.2018.05.006
文献标志码:
A
摘要:
论文依托新建兰渝高铁桃树坪富水弱胶结粉细砂隧道工程,基于现场监测和数值模拟分析相结合的方法,对大断面富水砂地层条件下的隧道施工方案进行了优化和分析,研究了大断面隧道CRD法、双侧壁导坑法和三台阶七步法三种施工方案的优缺点,改进了大断面隧道双侧壁导坑法施工技术,提出了“底部双导洞超前施工”的新工法。跟踪桃树坪隧道 3#斜井施工工区底部双导洞超前工法试验段进行的现场围岩压力、拱顶沉降和水平位移的现场监测,验证了工法的安全、可行性;基于数值模拟分析,确定了施工中上半断面的最佳开挖高度 5.4 m,超前导洞1部与上半断面5部间合理步距 25 m,优化了底部双导洞超前施工工法的技术参数,为富水弱胶结粉细砂地层隧道的施工提供了技术保障。
Abstract:
Taoshuping tunnel, the new constructed of Lanzhou-Chongqing railway, has a complicated geological condition of rich water and weak cemented fine sand. Combined with the method of in-situ monitoring and numerical simulation, the large cross-section tunnel construction scheme under the geological condition of rich-water and fine sand are analyzed and optimized. On the basis of compared the advantages and disadvantages by CRD method, double-side-drift method and three steps seven footwork excavation method, the double-side-drift method for large cross-section is improved and a new method of bottom advanced double-drift method is proposed. The security and feasibility of the new method are proved by in-situ monitoring the surrounding rock pressure, vault settlement and horizontal convergence of Taoshuping tunnel 3# inclined shaft’s test section. Based on the numerical simulation, the technical parameters for the new method is optimized. The simulation results show that the optimum excavation height of upper section is 5.4 m and the most reasonable step distance between the 1st part (advanced double-drift) and the 5 th part (upper section) is 25 m. The research results provided a technical support for tunnel construction under the condition of rich and weak cemented fine sand stratum.

参考文献/References:

参考文献 References[1] 宋战平, 张丹锋, 曲建生,等. 承压富水砂土地层桩洞法施工变形控制研究[J]. 西安建筑科技大学学报(自然科学版), 2015, 47(1): 33-38.SONG Zhanping, ZHANG Danfeng, QU Jiansheng, et al. Study on the deformation control of PBA construction method in pressure water sand stratum[J]. J. Xi’an Univ. of Arch. & Tech. (Natural Science Edition), 2015, 47(1): 33-38.[2] 易小明, 张顶立, 陈铁林. 厦门海底隧道地层变形监测与机制分析[J]. 岩石力学与工程学报, 2007, 26(11): 2302-2308. YI Xiaoming, ZHANG Dingli, CHEN Tielin. Stratum deformation monitoring and mechanism analysis of Xia-men subsea tunnel[J]. Chinese Journal of Rock Mechanics and Engineering, 2007, 26(11): 2302-2308.[3] 吉小明, 吕纬. 含水砂层隧道围岩失稳破坏机制及控制研究现状综述[J]. 岩土力学, 2009, (S2): 291-296.JI Xiaoming, LÜ Wei. Review of research on instability failure mechanism and stability control of tunnel sur-rounding rock in water-bearing sandy ground[J]. Rock and Soil Mechanics, 2009, 30(S2): 291-297.[4] 何珺, 张成平, 杨公标. 砂卵石地层小净距隧道渐进性破坏过程试验研究[J]. 土木工程学报, 2015, 48(S1): 362-367.HE Jun, ZHANG Chengping,YANG Gongbiao. Test study on progressive failure of closely spaced tunnel in sandy cobble ground[J]. China Civil Engineering Journal, 2015, 48( S1) : 362-367.[5] 何川,曾东洋. 砂性地层中地铁盾构隧道管片结构受力特征研究[J]. 岩土力学, 2007, 28(5): 909-914.HE Chuan, ZENG Dongyang. Research on mechanical characteristics of metro shield tunnel segment in sandy strata[J]. Rock and Soil Mechanics, 2007, 28(5): 909-914.[6] 张旭东. 土压平衡盾构穿越富水砂层施工技术探讨[J]. 岩土工程学报, 2009, 31(9): 1445-1449.ZHANG Xudong. Construction technology of earth pressure balance shield in watery sandy stratum[J]. Chi-nese Journal of Geotechnical Engineering, 2009, 31(9): 1445-1449.[7] 罗平. 含水弱胶结砂岩隧道地层特性及施工技术研究[D]. 北京: 北京交通大学,2011.LUO ping. Research on the engineering properties and tunnelling construction technologies of poorly cemented sandstone aquifer [D]. Beijing: Beijing Jiaotong Univer-sity, 2011.[8] 郭振超. 穿越富水饱和粉细砂地层双线客专隧道综合施工技术研究[D]. 西安: 西安建筑科技大学, 2013.GUO Zhenchao. Through the research on construction technique of saturated water rich sand stratum double passenger tunnel[D]. Xi’an: Xi’an Univ. of Arch. & Tech.: 2013.[9] SONG Z P, YANG T T, JIANG A N, et al. Experimental investigation and numerical simulation of surrounding rock creep for deep mining tunnels[J]. Journal of the Southern African Institute of Mining & Metallurgy, 2016, 116(12): 1181-1188.[10] LEE I M, NAM S W. The study of seepage forces acting on the tunnel lining and tunnel face in shallow tunnels[J]. Tunnelling and Underground Space Technology, 2001, 16(1): 31-40.[11] LEE I M, NAM S W, AHN J H. Effect of seepage forces on tunnel face stability[J]. Canadian Geotechnical Journal, 2003, 40(2): 342-350.[12] BRACHMAN R W, MARTIN C D, GILLISS S A. Grout field trials in outwash sands[J]. Canadian Geotechnical Journal, 2004, 41(1): 1-11.[13] LEE S W, JUNG J W, NAM S W, et al. The influence of seepage forces on ground reaction curve of circular opening[J]. Tunnelling and Underground Space Tech-nology Incorporating Trenchless Technology Research, 2007, 22(1): 28-38.[14] 张建斌. 厦门翔安海底隧道陆域段CRD法位移监测分析[J]. 岩石力学与工程学报, 2007, 26(S2): 3653-3658.ZHANG Jianbin. Displacement monitoring analysis of Xiamen Xiang’an subsea tunnel in landside section con-structed with CRD method[J]. Chinese Journal of Rock Mechanics and Engineering, 2007, 26(S2): 3653-3658.[15] 王秀英, 谭忠盛, 王永红, 等. 兰渝铁路含水弱胶结砂岩隧道地层特性试验研究[J]. 土木工程学报, 2015, 48(S1): 191-195. WANG Xiuying, TAN Zhongsheng, WANG Yonghong, et al. Experimental investigation on the formation char-acteristics for weakly cemented sandstone aquifer tunnels in Lan-Yu Railway Line[J]. China Civil Engineering Journal, 2015, 48(S1): 191-195.[16] 韩现民. 西格二线关角隧道浅埋砂层段施工技术及力学效应研究[J]. 岩土力学, 2010, 31(S2): 297-302.HAN Xianmin. Study of construction technology and mechanical effect of Guanjiao tunnel in shallow-buried sandy stratum in Xining-Golmud 2nd Line[J]. Rock and Soil Mechanics, 2010, 31(S2): 297-302.[17] 苏秀婷. 青岛地铁富水砂层隧道开挖施工风险与变形规律研究[D]. 青岛: 中国海洋大学, 2012.SU Xiuting. Research of tunnel excavation risk and set-tlement in water-enriched soil layers of Qingdao metro[D]. Qingdao: Ocean University of China, 2012.

相似文献/References:

[1]宋战平,刘 京,吴焕通,等.长陡斜井钢纤维喷射混凝土单层衬砌试验研究[J].西安建筑科技大学学报(自然科学版),2013,45(03):348.[doi:10.15986/j.1006-7930.2013.03.008]
 SONG Zhan-ping,LIU Jing,WU Huan-Tong,et al.Experimental research on single-layer tunnel lining of steel fiber shotcrete and the application in motenlin deviated well[J].J. Xi’an Univ. of Arch. & Tech.(Natural Science Edition),2013,45(05):348.[doi:10.15986/j.1006-7930.2013.03.008]
[2]宋战平、,杨腾添,张丹锋,等.溶洞对隧道(洞)稳定性影响的数值试验及现场监测分析[J].西安建筑科技大学学报(自然科学版),2014,46(04):484.[doi:10.15986/j.1006-7930.2014.04.005]
 SONG Zhanping YANG TengtianZHANG DanfengLI Ning.Experiments and field monitoring and analysis about the impact of existing cave on the stability of the tunnel[J].J. Xi’an Univ. of Arch. & Tech.(Natural Science Edition),2014,46(05):484.[doi:10.15986/j.1006-7930.2014.04.005]
[3]张新柳.基于超前预报信息的隧道围岩分级及工程应用研究[J].西安建筑科技大学学报(自然科学版),2016,48(05):648.[doi:10.15986/j.1006-7930.2016.05.006]
 ZHANG Xinliu.Study on the classification and application of the tunnel s surrounding rock based on geological information forecast[J].J. Xi’an Univ. of Arch. & Tech.(Natural Science Edition),2016,48(05):648.[doi:10.15986/j.1006-7930.2016.05.006]
[4]宋战平,李世豪,张学钢,等.基于修正Peck法的隧道施工全地层变形规律研究[J].西安建筑科技大学学报(自然科学版),2018,50(02):190.[doi:10.15986/j.1006-7930.2018.02.006]
 SONG ZhanpingLI ShihaoZHANG XuegangWANG JunbaoWANG Tao.Study on strata settlement regular pattern induced by[J].J. Xi’an Univ. of Arch. & Tech.(Natural Science Edition),2018,50(05):190.[doi:10.15986/j.1006-7930.2018.02.006]
[5]王家滨,牛荻涛.硝酸侵蚀喷射混凝土NO-3扩散研究[J].西安建筑科技大学学报(自然科学版),2019,51(01):75.[doi:10.15986/j.1006-7930.2019.01.012]
 WANG Jiabin,NIU Ditao.Study on nitrate ion diffusion of lining shotcrete exposed to nitric acid[J].J. Xi’an Univ. of Arch. & Tech.(Natural Science Edition),2019,51(05):75.[doi:10.15986/j.1006-7930.2019.01.012]
[6]黄金,赵淼.基于贝叶斯网络的隧道围岩失稳风险分析[J].西安建筑科技大学学报(自然科学版),2019,51(04):545.[doi:10.15986/j.1006-7930.2019.04.012]
 HUANG Jin,ZHAO Miao.Risk analysis of tunnel surrounding rock based on Bayesian network[J].J. Xi’an Univ. of Arch. & Tech.(Natural Science Edition),2019,51(05):545.[doi:10.15986/j.1006-7930.2019.04.012]
[7]牛泽林,刘朝鹏,郑 蕾,等.大断面公路板岩隧道开挖与支护数值模拟研究[J].西安建筑科技大学学报(自然科学版),2020,52(03):376.[doi:10.15986/j.1006-7930.2020.03.010]
 NIU ZeLin,LIU Chaopeng,ZHENG Lei,et al.Numerical simulation study on excavation and support of slab tunnel in large section highway[J].J. Xi’an Univ. of Arch. & Tech.(Natural Science Edition),2020,52(05):376.[doi:10.15986/j.1006-7930.2020.03.010]
[8]周 文.下穿既有运营公路大断面浅埋隧道方案优选及监测分析[J].西安建筑科技大学学报(自然科学版),2020,52(04):520.[doi:10.15986-j.1006-7930.2020.04.008]
 ZHOU Wen.Scheme optimization and monitoring analysis of large section shallow buried tunnel on existing highway[J].J. Xi’an Univ. of Arch. & Tech.(Natural Science Edition),2020,52(05):520.[doi:10.15986-j.1006-7930.2020.04.008]
[9]刘彦涛.下穿寺庙隧道爆破振动影响的数值模拟与分析[J].西安建筑科技大学学报(自然科学版),2021,53(02):160.[doi:10.15986/j.1006-7930.2021.02.002]
 LIU Yantao.Numerical simulation and analysis of the influence of blasting vibration in the tunnel crossing under a temple[J].J. Xi’an Univ. of Arch. & Tech.(Natural Science Edition),2021,53(05):160.[doi:10.15986/j.1006-7930.2021.02.002]
[10]宋战平,王双院,苏春生,等.黄土地层浅埋小净距非对称断面隧道施工方案优化[J].西安建筑科技大学学报(自然科学版),2022,54(05):646.[doi:10.15986/j.1006-7930.2022.05.002 ]
 SONG Zhanping,WANG Shuangyuan,et al.Optimization of construction scheme for shallow buried tunnel with small spacing asymmetric section in loess stratum[J].J. Xi’an Univ. of Arch. & Tech.(Natural Science Edition),2022,54(05):646.[doi:10.15986/j.1006-7930.2022.05.002 ]

备注/Memo

备注/Memo:
基金项目:国家自然科学基金项目(51578447);住房和城乡建设部科学技术计划项目(2017-K4-032);陕西省教育厅专项科研计划项目(16JK1448)
 收稿日期:2017-05-12 修改稿日期:2018-07-25
作者简介:宋战平(1974-),男,博士生导师,主要研究岩土工程设计理论.E-mail: songzhpyt@xauat.edu.cn
更新日期/Last Update: 2018-11-21